Monthly Archives: June 2009

Gateway changes to ey02 completed without incident

We will be pushing changes to the ey02 gateways shortly

All clusters were in good form and we experienced no failures. Thanks!

Our west coast data center will be conducting preventative maintenance on an uninterrupted power supply system on 07/09/2009 at 20:00 to 07/10/2009 at 06:00 (GMT -8). Herakles Data engineers will work closely on-site with equipment system vendors and service providers to assure that the preventative maintenance is non-intrusive. This activity is fully scripted and designed to be transparent to your operations.

Downtime Expected — None.
Duration — 10 hours.

Aside from maintenance on ey00, all other clusters were in good form and we experienced no other failures. Thanks!

The gateway push for ey01, ey03 and ey06 completed without incident

We will be pushing gateway changes for ey01, ey03 and ey06

All slices on EY00 are back online and appear to be functioning as expected. We have verified that all sites are back online. If you experience any issues please open a ticket with us at http://support.engineyard.com.

All slices appear to be online. We are continuing to verify that they are functioning correctly.

All nodes are functioning properly. We are now starting all slices. As they are coming back online, we will be verifying that they are functioning normally.